Problem 1 - The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is given. Draw the Gantt chart for the whole construction activity.
CODE
|
ACTIVITY
|
DESCRIPTION
|
TIME (IN HOURS)
|
IMMEDIATE PREDECESSOR(S)
|
A
|
Planning
|
Find location; determine resource requirements
|
20
|
None
|
B
|
Purchasing
|
Requisition of lumber and sand
|
60
|
Planning
|
C
|
Excavation
|
Dig and grade
|
100
|
Planning
|
D
|
Sawing
|
Saw lumber into appropriate sizes
|
30
|
Purchasing
|
E
|
Placement
|
Position lumber in correct locations
|
20
|
Sawing, excavation
|
F
|
Assembly
|
Nail lumber together
|
10
|
Placement
|
G
|
Infill
|
Put sand in and under the equipment
|
20
|
Assembly
|
H
|
Outfill
|
Put dirt around the equipment
|
10
|
Assembly
|
I
|
Decoration
|
Put grass all over the garden, landscape, paint
|
30
|
Infill, outfill
|
Problem 2 - Refer to the table in Problem 1.
a) Draw the AON network for the construction activity.
b) Draw the AOA network for the construction activity.