Activity Rates
Refer to the information for Botas Company on the previous page. The following activity data have been collected:
Cutting
|
$150,000
|
Assembling
|
187,500
|
Inspecting
|
45,000
|
Reworking
|
22,500
|
Required:
Calculate the activity rates that would be used to assign costs to each product.