Question: 1. What advantages do CPM diagrams have over conventional bar graph schedules?
2. Redraw the accompanying network diagram, adding early and late event times to the diagram. Mark the critical path. Prepare an activity-time tabulation showing early start, late start, early finish, late finish, and total float.