On January 15, 2013, Talbot Corporation purchased a parcel of land as a factory site for $425,000. An old building on the property was demolished, and construction began on a new building which was completed on November 31, 2013. Salvaged materials resulting from the demolition were sold for $12,000. Costs incurred during this period included: Demolition of old building, $35,000, Architect's fees, $15,000, Legal fees for title investigation and purchase contract, $7,000, and Construction costs, $980,000. Talbot should record the cost of the land and new building, respectively, as
$425,000 and $980,000
$455,000 and $995,000
$460,000 and $995,000
$460,000 and $983,000