Record changes that would affect the project


A document that is completed when a customer changes a specification, delivery method or place, and so on, whose purpose is to record changes that would affect the project's remaining true to the original contract is called a _____________________.

1) tracking order

2) change order

3) project order

4) project log

Select the correct answer from the choices above and provide your reference for your selection.