A document that is completed when a customer changes a specification, delivery method or place, and so on, whose purpose is to record changes that would affect the project's remaining true to the original contract is called a _____________________.
1) tracking order
2) change order
3) project order
4) project log
Select the correct answer from the choices above and provide your reference for your selection.