Reconfigure the chart above into a critical path diagram


Assignment

In a 1-page Word document, consider the following activities and their durations. The original project schedule, using early activity starts, is shown below.

Activity

Task

Predecessors

Duration

Activity Cost

A

Sign Contract

None

5 days

$5,000

B

Design Survey

A

3 days

$1,500

C

Identify Audience

A

7 days

$1,000

D

Run Survey

B, C

30 days

$6,000

E

Analyze Results

D

5 days

$3,000

F

Create Presentation

E

5 days

$1,000

G

Present to Client

E, F

2 days

$3,000

• Reconfigure the chart above into a critical path diagram for project scheduling similar to the diagram shown in this module's lecture.
• What is the duration of the project?
• How much slack is currently available in the non-critical path?
• How long are the project and feeder buffers?