Lytherma Construction entered into a contract to construct a floating bridge across a lake. The contract price for the bridge is 7,500,000. During 2005, costs of 1,800,000 were incurred representing 30% of total expected costs.
Prepare the necessary entries for 2005 to recognize gross profit for the year assuming the firm uses the
1. completed-contract method
2. percentage-of-completion method