Recently you were assigned to manage a project for your


Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project? (shown below to the? right). In? addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following? table. What is the expected completion time of the? project?

Activity Optimistic (days) Most Likely (days) Pessimistic (days)

A 4 8 12

B 5 9 11

C 5 7 8

D 1 4 5

E 3 8 9