Response to the following problem:
Calculate and suggest possible reasons for the materials usage variance from the following data:
Standard price per tonne is £50
Standard usage is 1.000 tonnes
Actual price per tonne is £50
Actual usage is 995 tonnes
Show all work and calculations.