Question
Using a project drawn from your own experience, discuss the following-
(a) What are the two primary stages of risk management of a project?
(b) What are the four possible choices in allocating the risks of a project? Give a brief description of those four choices
(c) What are the sources, effects and four types of risks in engineering projects?