Question:
The Daytona Company is involved in a 3-year long-term contract. The subsequent data relate to this contract:
2010       2011       2012       Total
Contract price     $160,000
Cost incurred each year           $24,000 $24,000 $ 56,000                104,000
Cost incurred to date                  24,000   48,000   104,000
Estimated cost to complete            96,000   48,000   0             
Partial billings each year                12,000   48,000   100,000
Cash collected from billings             8,000     52,000   100,000
Write the journal entries to reflect the percentage-of-completion method for 2011: 18 points
a. Construction costs for the year.
b. Partial billings.
c. Cash collections.