Question:
a)  List and explain three project Estimation techniques.
b) During an estimation exercise, a work breakdown structure (WBS) is used as checklist for the activities in a project.  How can the WBS help in the estimation activity?  What are the limitations of such an approach?
c)  How can the above method be improved?