Question :

Platypus Building Inc. won a bid for a new office building contract. Below is info from the project accountant:    

Total Construction Fixed Price                      $8,000,000             

Construction Start Date                           March 3, 2012        

Construction Complete Date                    December 4, 2014                                             

As of Dec 31...                                2012                            2013       

Actual cost incurred  per year         2,000,000                 $1,000,000  

Estimated costs to complete         $ 2,000,000                   $1,000,000                 

Billed to customer                        $2,400,000                 $5,300,000       

Received from customer               $2,250,000                $5,400,000  

Consider Platypus Building Inc. uses the percentage of completion technique, what amount of gross profit would be recognized in 2013?

Request for Solution File

Ask an Expert for Answer!!
Financial Accounting: question platypus building inc won a bid for a
Reference No:- TGS0445297