The project started and your immediate supervisor asked for a field report on day 10. The field report you submitted on day 10 is given below.
Field Report at Day 10
|
Activity
|
Actual Completion %
|
Cost Incurred
|
A
|
100
|
2400
|
B
|
100
|
1200
|
C
|
100
|
4000
|
D
|
80
|
4000
|
E
|
25
|
4000
|
F
|
0
|
0
|
Question: Calculate the BCWP, BCWS, CPI, SPI, CV, and SV for the field report day 10. Show your calculations, and summarize the results on a table.