Question at the end of one of my chapters. Would like to see an example of cost and schedule performance index completed. I appreciate the help
A sales-related venture had an actual cost of $34k, a planned cost of $42k, and a value completed of $39k. Calculate the CPI and SPI. Explain the results of the calculation - what do they mean?