QUESTION 1
(a) What do you understand by the term Scheduling?
(b) Explain how the following ways for duration compression of a project can be achieved-
(c) Distinguish between a Project Charter and a Project Plan
QUESTION 2
(a) Differentiate between Quality and Grade
(b) What do you understand by each of the following Quality Management Approach-
- Deming cycle
- Juran trilogy
- Crosby four absolutes
- Taguchi
- Kaizen
(c) Enumerate 4 issues which may give rise to direct total cost in the management of quality of a project
QUESTION 3
In grouping members to form a project management team, the problem arises when there should be a mix of both local and international employees. A criteria checklist should be developed based on the assessment of the international skills and abilities. Explain the four requirements which should be included in such a criteria checklist