Question 1 Explain the various inputs , tools and techniques of qualitative risk analysis process
Question 2 The risk mitigation methodology describes the approach to control implementation. Explain the steps of the methodology
Question 3 There are two main strategies to handle risks, negative risks and positive risks . Explain the Response strategies for threats (Negative Risks)
Question 4 What are the tips to remove the top three project estimating risks? Explain in brief
Question 5 An organisation building a risk-based culture must offer incentives for incorporating risk into the project planning and control process. Analyse the concept of performance incentive
Question 6 Explain project reviews and Risk Reassessment briefly