Quantity and time frame


A) Which of the following is considered an organizational blueprint, which prescribes the quantity and time frame for when each end product will be assembled?

• MRP (Material Requirements Plan)
• ERP (Enterprise Resource Planning)
• MPS (Master Production Schedule)
• WBS (Work Breakdown Structure)

B) There are many applications of poka-yokes in service organizations. Which of the following is one of the three-T's used to classify poka-yokes?

• Trust
• Teamwork
• Task
• Time