Q. Consider a project for which the manpower requirement is 200 PY and the development time is 2 years. calculate the peak manning time.
Ans Software Project cost K=200 PY
Peak development time td =2 year =2 years
Peak manning m0=(k/ td* sqrt(e))=200/2*1.648=164.8 »164 persons