Psh industries uses a kanab system to manage production of


Question: PSH Industries uses a Kanab system to manage production of the J-l5 subassembly, hey have an hourly demand for 250 units and use containers that can hold 50 units each. It takes 90 minutes to fill and move a container of parts to the right place on the MS line that is currently rated at a 20% safety factor. How many production cards are needed?