Provide the mrp tables for all the finished products


Product structure for the finished good product A is :
A consist of E(2) and D(3), with D(3) consist of C(1).

Use POM Software to Solve the MRP problem.

The marketing department is estimating product A's demand to be 60 units for week 4 and 50 units for week 6. There is a scheduled receipt of 75 units for component D at the beginning of week 2. Various other MRP related information for the finished products and the components are provided below.

A C D E
On hand 12 170 9 5
Lead Time 2 2 1 1
Lot Size LFL 150+ multiples of 40 multiples of 22

Provide the MRP tables for all the finished products and the components for the next 6 weeks.