Projects in terms of performance efficiency-budget-schedule


Analyze and compare the costs of the two projects in terms of performance efficiency, budget, and schedule. Make sure to show your calculations and analyze and explain the results. (Note: Providing just numbers will receive only partial credit.) Project A: The budgeted cost of work performed is $48,000, and the actual cost of work performed is $52,000. The budgeted cost of work scheduled is $54,000. (15 points)Project B: The budgeted cost of work performed is $108,000, and the actual cost of work performed is $200,000. The budgeted cost of work scheduled is $232,000.