Analyze and compare the costs of the two projects in terms of performance efficiency, budget, and schedule. Make sure to show your calculations and analyze and explain the results. (Note: Providing just numbers will receive only partial credit.) Project A: The budgeted cost of work performed is $48,000, and the actual cost of work performed is $52,000. The budgeted cost of work scheduled is $54,000. (15 points)Project B: The budgeted cost of work performed is $108,000, and the actual cost of work performed is $200,000. The budgeted cost of work scheduled is $232,000.