A manager must decide between two machines. The manager will take into account each machine operating costs and initial costs, and its breakdown and repair times. Machine A has a projected average operating time of 142 hours and a projected average repair time of 7 hours. Projected times for machine B are an average operating time of 65 hours and a repair time of 2 hours. What are the projected availabilities of each machine?