Problem:
A company is considering a project with a cash break-even point of 22,600 units. The selling price is $28 a unit, the variable cost per unit is $13, and depreciation is $14,000.
Requirement:
Question: What is the projected amount of fixed costs?
- $325,000
- $339,000
- $342,000
- $348,000
- $353,000
Note: Please show the work not just the answer.