Project Y has a cost of $50,000,000 today. Project Y will have cash flows of $18,000,000 the first year ,$19,000,000 the second year and $23,000,000 the third year. Calculate the NPV and the IRR using 10% capital. Please show work by using two methods (1) identifying all variables using the calculator’s function keys,(2)using the steps on the calculator to calculate the NPV and the IRR.