Project with the highest internal rate of return


Problem: Green Grocers is deciding among two mutually exclusive projects. The two projects have the following cash flows:

Year Project A Cash Flow Project B Cash Flow

0 -$50,000 -$30,000
1 10,000 6,000
2 15,000 12,000
3 40,000 18,000
4 20,000 12,000

The company's weighted average cost of capital is 10 percent (WACC = 10%). What is the net present value (NPV) of the project with the highest internal rate of return (IRR)?

$ 7,090

$ 8,360

$11,450

$12,510

$15,200

Solution Preview :

Prepared by a verified Expert
Finance Basics: Project with the highest internal rate of return
Reference No:- TGS01815957

Now Priced at $20 (50% Discount)

Recommended (95%)

Rated (4.7/5)