Project stakeholder influence, risk, and "cost of changes" may change over time as a project progresses to completion. Identify the ONE correct statement regarding the changes for stakeholder influence, risk or "costs of changes" during the life of a project.
a) Project sponsor (customer) influence goes up
b) Project manager influence remains constant
c) The number of risks always go up
d) Cost of changes goes down
e) Program manager influence always goes down