Project risk typically is characterized by which three factors?
a) impact, duration of the impact, and cost of the impact
b) quality of the event, time, and procurement scope
c) risk event, probability of risk, and consequences of the risk
d) frequency of the event, impact to the sponsor, and alignment with the project scope