Project Manager Buddy Lee has elected to use a Firm Fixed-Price contract type for his procurement. Which type of Procurement Document(s) are most appropriate for Buddy Lee to use?
A. RFP, RFI, or RFQ
B. RFP or FFP
C. RFP or RFQ
D. RFI or RFQ
Note Please include supporting rationale for the answer selected.