project management questionsthroughout a project


Project Management: Questions

Throughout a project, the Cost Performance Index has decreased from 1.3 to 0.8. The cost performance on this project has:

a. Improved.
b. Deteriorated.
c. Stayed about the same.
d. There is insufficient information to answer the question.

Question
Which of the following statements best describes the relationship between project cost and quality?

a. Six Sigma method has no relationship to project cost management.
b. Improved quality results in higher total life cycle cost.
c. Quality should be planned into the project to reduce total life cycle cost.
d. Quality is primarily a manufacturing issue and has no impact on project cost.

Question
If cumulative PV = ?100,000, cumulative EV = ?98,000, and cumulative AC = ?104,000, the project is:

a. Ahead of schedule.
b. Operating below project cost projections.
c. Likely to come in over budget at completion.
d. Likely to come in under budget at completion.

Question

Which of the following methods is most likely to result in an increase in project cost?

a. Earned value method
b. Trade-off decisions involving resources, schedule, and performance
c. Resource leveling
d. Crashing activities to meet end dates

Question

In which type of cost estimating is regression analysis technique used?

a. Bottom-up
b. Definitive
c. Parametric
d. Engineering (grass roots)

Request for Solution File

Ask an Expert for Answer!!
Project Management: project management questionsthroughout a project
Reference No:- TGS0472733

Expected delivery within 24 Hours