Project management-cpm-pert techniques


Problem: Using the following project information

Activity

 

Optimistic Time
Estimate(weeks)

 

Most Likely Time
Estimates (weeks)

 

Pessimistic Time
Estimates (weeks)

 

Immediate
Predecessor(s)

 

Variance

 

Expected Time
(weeks)


A

 

3

 

6

 

9

 

none

 

1.000

 

6.00

B

 

3

 

5

 

7

 

A

 

0.444

 

5.00

C

 

4

 

7

 

12

 

A

 

1.778

 

7.33

D

 

4

 

8

 

10

 

B

 

1.000

 

7.67

E

 

5

 

10

 

16

 

C

 

3.361

 

10.17

F

 

3

 

4

 

5

 

D,E

 

0.111

 

4.00

G

 

3

 

6

 

8

 

D,E

 

0.694

 

5.83

H

 

5

 

6

 

10

 

F

 

0.694

 

6.33

I

 

5

 

8

 

11

 

G

 

1.000

 

8.00

J

 

3

 

3

 

3

 

H,I

 

0.000

 

3.00


The critical path is A-C-E-G-I-J.

(a) Calculate the probability that the project will be completed in 38 weeks.

P(project ≤ 38) =

(b) Calculate the probability that the project will be completed in 42 weeks.

P(project ≤ 42) =

(Round your answers to 3 decimal places, the tolerance is +/-0.005.)

Solution Preview :

Prepared by a verified Expert
Project Management: Project management-cpm-pert techniques
Reference No:- TGS01954006

Now Priced at $20 (50% Discount)

Recommended (94%)

Rated (4.6/5)