Problem:
WeCare is evaluating a new project. It has a coefficient of variation (CV) of 5, while the HMO's average project has a CV of 2-3. The business's corporate cost of capital is 10 precent, and the typical adjustment for project risk is three percentage points.
Required:
Question: What is the project cost of capital?
Note: Show supporting computations in good form.