Relevant information for project consisting of activities A, B, C, H is provided in table below and the project network is given.
Activity
|
Immediate Predecessors
|
Time in weeks
|
A
|
N/A
|
3
|
B
|
A
|
4
|
C
|
A
|
6
|
D
|
B, C
|
9
|
E
|
C
|
6
|
F
|
B
|
2
|
G
|
D, E
|
5
|
H
|
F, G
|
8
|
What is earliest start time for the activity G?