Project consisting of activities


Relevant information for project consisting of activities A, B, C, H is provided in table below and the project network is given.

Activity

Immediate Predecessors

Time in weeks

A

N/A

3

B

A

4

C

A

6

D

B, C

9

E

C

6

F

B

2

G

D, E

5

H

F, G

8

What is earliest start time for the activity G?