Question: Project A has an internal rate of return (IRR) of 21 percent in 2 years. Project B has an IRR of 17 percent in 3 years. Project C has an IRR of 31 percent in 2.5 years. Project D has an IRR of 29 percent in 1 year. Which of these would be the BEST project for implementation financially?