Question: Project A: (-2,000, 500, 600, 700, 800) Project B: (-2000, 950, 850, 400, 300) If the discount rate is 12%, what is the discounted payback period for project A, and B? At what discount rate will we be indifferent between A and B? The response must be typed, single spaced, must be in times new roman font (size 12) and must follow the APA format.