The purpose of this simulation project is to provide you with an opportunity to use the POM-QM for Windows software to solve an MRP problem.
POM-QM for Windows software
For this part of the Individual Project, you need to use the POM-QM for Windows software:
- Read Appendix IV of the Operations Management (Heizer & Render, 2011) textbook.
- Launch the POM-QM for Windows software and from the main menu select Module, and then Materials Resource Planning.
- Program the MRP for the Individual Project Problem below and solve it with the use of POM-QM for Windows. (Refer to Appendix IV in the Heizer and Render (2011) textbook.)
Individual Project ProblemThe product structure tree for the finished product A is given below.
A-----------------------D(3)-------------------C(1)
----------------------------E(2)
The marketing department is estimating product A's demand to be 60 units for week 4 and 50 units for week 6. There is a scheduled receipt of 75 units for component D at the beginning of week 2. Various other MRP related information for the finished products and the components are provided below.
|
A
|
C
|
D
|
E
|
On hand
|
12
|
170
|
9
|
5
|
Lead time
|
2
|
2
|
1
|
1
|
Lot size
|
LFL
|
150+
|
multiples of 40
|
multiples of 22
|
Provide the MRP tables for all the finished products and the components for the next six weeks.