Profitability Index versus NPV. Consider these two projects:

Project    C 0    C 1    C 2    C 3
A     -$36    +$20    +$20    +$20
B      - 50    + 25     + 25    + 25

A. Which project has the higher NPV if the discount rate is 10 percent?

B. Which has the higher profitability index?

C. Which project is most attractive to a firm that can raise an unlimited amount of funds to pay for its investment projects? Which project is most attractive to a firm that is limited in the funds it can raise?

Please help me with answers and WORK to these questions so that I can learn how to perform these problems.