I) Which of the following is one of Dr. Eli Goldratt's rules of production scheduling for optimized production technology?
• An hour saved at a bottleneck operation does not increase the process flow.
• If you lose an hour at a bottleneck it is better than making scrap.
• Do not allow bottlenecks to govern the flow of the line.
• Utilization and activation of a resource are not the same.
II) Which is the one correct value stream principle?
• Look for efficiencies in the factory, office, physical, procedural, and technical operations.
• Eliminate waste that stops, slows down, or diverts the value stream.
• Concentrate on speeding up value-adding operations rather than removing waste.
• Keep the value stream moving at minimum velocity.