Production of cost estimator


Assignment:

Manceville Air has just produced the first unit of a large industrial compressor that incorporated new technology in the control circuits and a new internal venting system. The first unit took 112 hours of labor to manufacture. The company knows from past experience that this labor content will decrease significantly as more units are produced. In reviewing past production data, it appears that the company has experienced a 90% learning curve when producing similar designs. The company is interested in estimating the total time to complete the next 7 units. Your job as the production cost estimator is to prepare the estimate.

Provide complete and step by step solution for the question and show calculations and use formulas.

Solution Preview :

Prepared by a verified Expert
Operation Research: Production of cost estimator
Reference No:- TGS01954061

Now Priced at $30 (50% Discount)

Recommended (99%)

Rated (4.3/5)