Product A is an end item and is made from two units of B and four of C. B is made of three units of D and two of E. C is made of two units of F and two of E.
A has a lead time of one week. B,C, and E have lead times of two weeks, and D and F have lead times of three weeks.
- Show the bill of materilas (product structure tree)
- If 100 units of A are required in Week 10, develop the MRP planning schedule, specifying when items are to be ordered and received. There are currently no units of inventory on hand.