Product A consists of sub assembly's D and C. For every A you require one of D and 2 of C. Sub assembly C requires 2 parts of D and one of B.
a. Draw the BOM for this product A.
b. Assume the mast schedule calls for 200 units of product A in week 5 and 250 units in week 6. Build a materials plan.
c. What actions should be taken immediately?