Risk Factors and Gantt Charts
Question 1: Project Risk factors
• List the major risk factors for your project and the possible ways to mitigate this risks for your project.
Question 2: Resource Evaluation
• Produce and complete a Gantt Chart using MS Project software.
• Using the Table below enter the information into MS Project software. Assume that each resource has been assigned to the project activity on a full-time (8 hours /day or 40 hours per week) basis
Activity
|
Duration
|
Predecessors
|
Resource Assigned
|
A. User Survey
|
4
|
None
|
Gail Wilkins
|
B. Coding
|
12
|
A
|
Tom Hodges
|
C. Debugging
|
5
|
B
|
Wilson Pitts
|
D. Design Interface
|
6
|
A,C
|
Sue Ryan
|
E. Develop Training
|
5
|
D
|
Reed Taylor
|