Problem: Reorder the lists to show the process of developing a schedule for a project. Note: Drag the activity and place it at its correct position (i.e., if defining activities is the first step, then, drag it and place it at the 1st blank box). a. Assign durations to activities b. Calculate early and late start/finish times c. Schedule activity start/finish times d. Break down the project into manageable activities e. Compute float values and identify the critical path f. Sequencing of activities g. Determine the relationships between the activities and draw a network diagram h. Assign resources