9.1-  Use the chi-square goodness-off-fit test and a significance level of 0.1  to test the set of interarrival times in Table 9.32 for possible fit to  the exponential distribution.
TABLE 9.,3 2
Interarrival times for Exercise 9.1
    
| 1.9 | 
5.3 | 
1.1 | 
4.7 | 
17.8 | 
44.3 | 
| 9 | 
18.9 | 
114.2 | 
47.3 | 
47.1 | 
11.2 | 
| 60.1 | 
38.6 | 
107.6 | 
56.4 | 
10 | 
31.4 | 
| 58.6 | 
5.5 | 
11.8 | 
62.4 | 
24.4 | 
0.9 | 
| 44.5 | 
115.8 | 
2 | 
5.03 | 
21.1 | 
2.6 | 
9.5- Apply the KS test to the data in Exercise 9.1.
Process Modeling and Analysis in an Assembly Factory
The  LeedsSim factory is a traditional assembly facility working as a  subcontractor to the telecommunications industry. Their main product is a  specialized switchboard cabinet used in the fourth-generation (4G)  network base stations. The company has been successful on the sales  side, and with the AG expansion taking off, the orders are piling up.  Unfortunately, the operations department has had some problems with  reaching the desired (and necessary) productivity levels. Therefore,  they have decided to seek help to create a simulation model process as a  step to analyze and improve the process design.
To find  the right level of detail in the model description, they want to start  with a simple model and then successively add more details until a  suitable model with the right level of complexity is obtained. The  simulation should be run over a 3 month (12 week) period of five 8 h  workdays/week. A schematic flowchart of the manufacturing process is  shown in Figure 9.35.
After the cabinets are completed and inspected,  the finished cabinets leave the factory. It is noteworthy that each  workstation can handle only one item at a time. Moreover, a forklift  truck is required to move the assembled cabinets. Workstations 1 through  3 cannot store items. Similarly, there is no room to store items before  workstations 4, but after it, there is room to store two assembled  cabinets. At workstation 5, there is ample space to store cabinets  before the workstation, but after it, there is only room to store at  most two painted cabinets. At the inspection station, there is space to  store cabinets both before and after the station.

Table 9.18
Estimated Processing and Inspection Times
 
    
| Processing   Unit | 
Processing Time Distribution | 
Parameter Values(h) | 
| Workstation 1 | 
triangular | 
Max = 3, min = 1.5, most likely = 2 | 
| Workstation 2 | 
triangular | 
Max = 3, min = 1.5, most likely = 2 | 
| Workstation 3 | 
triangular | 
Max = 3, min = 1.5, most likely = 2 | 
| Workstation 4 | 
triangular | 
Max = 4, min = 2, most likely = 3 | 
| Workstation 5 | 
triangular | 
Max = 6, min = 3, most likely = 4 | 
Each  cabinet that is made requires one unit each of five different  components/raw materials delivered to the inbound storage area.  Workstation 1 requires one unit each of raw materials 1 and 2,  workstation 2 requires one unit of raw material 3, and workstation 3  requires one unit each of raw materials 4 and 5. Table 9.18 specifies  the estimated processing times in workstations 1 through 5. Table 9.19  shows collected inspection time data that have not it been analyzed.  This needs to be done in order to build a valid model of the process.
The  performance measure that LeedsSim is must interested in is the number  of cabinets produced in a 3 month period. However they also want to keep  track of the following:
• The  WIP levels (measured in units of raw material)-the total as well as at  different parts of the workshop (the mean and the standard deviation for  a single run and the mar with 95% confidence intervals in case of  multiple simulation runs)
• The  inbound storage levels of the raw materials (the maximum, the mean,. and  the standard deviation for a single run and the mean with 95%  confidence intervals in case of multiple simulation runs)
• The  cycle time, measured from the instant a component arrives to the storage  area until a finished cabinet leaves the factory (the mean and the  standard deviation for a single run and the mean with 95% ) confidence  intervals in case of multiple simulation runs) (Hint.: Note that all  components for a particular cabinet have the same cycle time.)
Utilizations  of workstations and equipment such as the forklift truck (the mean wit h  95% confidence intervals in case of multiple simulation runs)
Table 9.19
Observed Inspection Time Data in Minutes
 
| 
 No. 
 | 
 Inspection Time 
 | 
 No. 
 | 
 Inspection Time 
 | 
 No. 
 | 
 Inspection Time 
 | 
 No. 
 | 
 Inspection Time 
 | 
| 
 1 
 | 
 0.944 
 | 
 31 
 | 
 0.21 Pl. 
 | 
 61 
 | 
 0.313 
 | 
 91 
 | 
 l.532 
 | 
| 
 2 
 | 
 3.08.4 
 | 
 32 
 | 
 1_49K 
 | 
 62 
 | 
 2.12'14 
 | 
 92 
 | 
 2.561 
 | 
| 
 3 
 | 
 0.169 
 | 
 33 
 | 
 .7._43 
 | 
   
 | 
 0.756 
 | 
 93 
 | 
 6.1%5 
 | 
| 
 4 
 | 
 7,078 
 | 
 34 
 | 
 1,491 
 | 
 64 
 | 
 0,991 
 | 
 94 
 | 
 1.663 
 | 
| 
 5 
 | 
 2.440 
 | 
 35 
 | 
 0.008. 
 | 
 65 
 | 
 1.001 
 | 
 95 
 | 
 0.9914 
 | 
| 
 6 
 | 
 5.A6 
 | 
 36 
 | 
 0,502 
 | 
 66 
 | 
 2.070 
 | 
 96 
 | 
 0,153 
 | 
| 
 7 
 | 
 0.201 
 | 
 37 
 | 
 2,324 
 | 
 67 
 | 
 3.216 
 | 
 477 
 | 
 13135 
 | 
| 
 8 
 | 
 1.185 
 | 
 34 
 | 
 0.4584 
 | 
 68 
 | 
 2.037 
 | 
 915 
 | 
 0.212 
 | 
| 
 9 
 | 
 5.308 
 | 
 39 
 | 
 1.474 
 | 
 69 
 | 
 5.358 
 | 
 99 
 | 
 0_757 
 | 
| 
 10 
 | 
 0.989 
 | 
 40 
 | 
 1_18.0 
 | 
 70 
 | 
 0.024 
 | 
 100 
 | 
 1191 
 | 
| 
 11 
 | 
 0.5W 
 | 
 41 
 | 
 4.307 
 | 
 71 
 | 
 2.397 
 | 
 101 
 | 
 0.063 
 | 
| 
 12 
 | 
 8.176 
 | 
 42 
 | 
 5.252 
 | 
 72 
 | 
 4.718 
 | 
 102 
 | 
 3.571 
 | 
| 
 13 
 | 
 3.676 
 | 
 43 
 | 
 6.797 
 | 
 73 
 | 
 1.478 
 | 
 103 
 | 
 7.869 
 | 
| 
 14 
 | 
 0.504 
 | 
 44 
 | 
 3 461 
 | 
 74 
 | 
 1.0843 
 | 
 104 
 | 
 0_233 
 | 
| 
 15 
 | 
 0.016 
 | 
 45 
 | 
 0_41E1 
 | 
 75 
 | 
 12.196 
 | 
 105 
 | 
 0.661 
 | 
| 
 16 
 | 
 1.392 
 | 
 46 
 | 
 0.699 
 | 
 76 
 | 
 0.109 
 | 
 106 
 | 
 0.697 
 | 
| 
 17 
 | 
 0.552 
 | 
 17 
 | 
 0293 
 | 
 77 
 | 
 4.355 
 | 
 107 
 | 
 4..437 
 | 
| 
 18 
 | 
 2.03 
 | 
 48 
 | 
 4.245 
 | 
 743 
 | 
 1.158 
 | 
 11-16 
 | 
 [P.1345 
 | 
| 
 19 
 | 
 2,&iN 
 | 
 444 
 | 
 1,594 
 | 
 79 
 | 
 0.003 
 | 
 109 
 | 
 1.239 
 | 
| 
 20 
 | 
 5,982 
 | 
 .-.47 
 | 
 ia,r33 
 | 
 mo 
 | 
 U.137 
 | 
 110 
 | 
 0,357 
 | 
| 
 2] 
 | 
 2.337 
 | 
 1.1 
 | 
 0,381.1 
 | 
 81 
 | 
 0.293 
 | 
 111 
 | 
 ] .143 
 | 
| 
 22 
 | 
 2.426 
 | 
 52 
 | 
 1.11C8 
 | 
 H2 
 | 
 0.193 
 | 
 112 
 | 
 3.0611 
 | 
| 
 23 
 | 
 0,252 
 | 
 53 
 | 
 1,457 
 | 
 83 
 | 
 1.263 
 | 
 113 
 | 
 0.5.48 
 | 
| 
 24 
 | 
 0.294) 
 | 
 54 
 | 
 0.206 
 | 
 84 
 | 
 2.249 
 | 
 114 
 | 
 3.460 
 | 
| 
 25 
 | 
 5139 
 | 
 55 
 | 
 0_755 
 | 
 85 
 | 
 0.6E9 
 | 
 115 
 | 
 1171 
 | 
| 
 26 
 | 
 1.727 
 | 
 56 
 | 
 1.786 
 | 
 86 
 | 
 2.376 
 | 
 116 
 | 
 3.4o1 
 | 
| 
 27 
 | 
 3.1359 
 | 
 57 
 | 
 0_510 
 | 
 87 
 | 
 0.729 
 | 
 117 
 | 
 3.0132 
 | 
| 
 28 
 | 
 3.356 
 | 
 58 
 | 
 3.400 
 | 
 88 
 | 
 1.408 
 | 
 118 
 | 
 0357 
 | 
| 
 19 
 | 
 13.884 
 | 
 59 
 | 
 1.6-913 
 | 
 89 
 | 
 5.199 
 | 
 119 
 | 
 1098 
 | 
| 
 30 
 | 
 1.992 
 | 
 60 
 | 
 2.186 
 | 
 90 
 | 
 3286 
 | 
 120 
 | 
 0.728 
 | 
Questions
1.  The raw material arrives by truck once every week on Monday morning.  Each shipment contains 15 units each of the five necessary components,  The internal logistics within the factory is such that the  transportation time for the incomplete Cabinets can be neglected.  However, to transport the assembled cabinet to and from the paint shop, a  special type of Forklift truck is needed. The transportation time from  the assembly line to the paint shop is exponentially distributed with a  mean of 45 min. The transportation time between the paint shop and the  inspection station of the loading, dock is normally distributed with a  mean of 60 min and a standard deviation of 15 min. After each delivery,  the forklift truck always returns to the strategically located parking  area to gel new instructions. The travel time for the forklift truck,  without between the parking area and each of the workstations is  negligible.
Transportation  of painted cabinets is prioritized. This means that whenever forklift  truck is available for a new assignment (as its parking area), and there  are unpainted and painted cabinets awaiting transport, the latter ones  will transported first. Currently one forklift truck is available in the  factory. For the first model, assume that all painted cabinets pass  inspection, so no rework occurs.
a.  Analyze the input data for the inspection times and fit a suitable  distribution. Build the model and run the simulation once with random  seed = 5. How many cabinets are being, produced? How is the WIP  situation? What does a plot over the storage inventory levels tell us?  Where is the bottleneck?
b. Run the simulation 30 times with  different randorn seeds. How many cabinets are being produced on  average? What is the standard deviation? How is the WIP situation? Where  is the bottleneck? (Hint: Use the Statistics block in the Value library  to collect data and analyze it efficiently. For the number of units  produced, use a Mean and Variance block, connect it to the exit block,  and check the dialogue options Calculate for Multiple Simulations and  use number of inputs-1.)
2. In  reality, only 75% of the painted cabinets pass the inspection. If a  cabinet fails the inspection, it needs to be transported back to the  paint shop to be repainted. The transportation time is the same as in  the opposite direction (normally distributed will a mean of 60 min and a  standard deviation of 15 min). The transportation of painted cabinets  that has failed inpection back to the paint shop has higher priority  than any other transportation assignment. The forklift truck will always  go back to the parking area after a completed mission. When arriving to  the paint shop, repainting has higher priority than the ordinary paint  jobs and follows an exponential distribution with a mean a 2 h.  Inspecting the reworked cabinets is no different from inspecting  non-reworked cabinets. How does the introduction of these features  affects the performance measures?
a. Run the simulation once with  random seed = 5. Flow many cabinets are being produced? How is the W1P  situation? Where is the bottleneck?
b. Run the simulation 30 times  with different random seeds. Flow many cabinets are being produced on  average? What is the standard deviation? Flow is the IN' IP situation?  Where is the bottleneck?
3.  Based on your understanding of the process, suggest a few design changes  and try them out. What is your recommendation to LeedsSim regarding how  to improve their operations?
4. In  this model, collection of statistics data starts at time zero, when the  system empty. It would be more accurate to run the system for a warm-up  period, say 1 week before starting to collect data. Implement this and  set the difference. Does it change your conclusions?