Problem
a. Explain Management Science models in detail.
b. Estimation the completion time of each activity whose optimistic time estimate is 5 seconds and the pessimistic time estimate are 20 seconds. The utmost likely time estimation is 9 seconds.
Things to do
a. Explanation
b. Formula te = to +tn+tp
-------------
6
The time of completion of each activity is equal to 10.1667