Problem on reducing duration of a non-critical activity


Question: In a project, reducing duration of a non-critical activity has the following effect? Group of answer choices A) The slack of the activity decreases, and project duration reduces B) The slack of the activity increases, and project duration does not change C) The slack of the activity decreases, and project duration does not change D) The slack of the activity increases, and project duration reduces

 