Problem on project network diagram


Assignment:

Given is a project network diagram as shown below:

1157_project network.JPG

Activity Start A B C D E F G H I J K End
Time 0 8 12 4 14 6 10 5 12 20 18 14 0

a) The Project Completion time =________________

b) The Earliest Start time, ES, of Activity F =_________________

c) The Earliest Start time, ES, of Activity K =_________________

d) The Latest Start time, LS, of Activity E =__________________

e) The non-critical activities are =__________________(ex. type in critical activities as ABCD, no comma, no space)

Start B End

Provide complete and step by step solution for the question and show calculations and use formulas.