Assignment:
Given is a project network diagram as shown below:
Activity |
Start |
A |
B |
C |
D |
E |
F |
G |
H |
I |
J |
K |
End |
Time |
0 |
8 |
12 |
4 |
14 |
6 |
10 |
5 |
12 |
20 |
18 |
14 |
0 |
a) The Project Completion time =________________
b) The Earliest Start time, ES, of Activity F =_________________
c) The Earliest Start time, ES, of Activity K =_________________
d) The Latest Start time, LS, of Activity E =__________________
e) The non-critical activities are =__________________(ex. type in critical activities as ABCD, no comma, no space)
Start B End
Provide complete and step by step solution for the question and show calculations and use formulas.