Problem on batch flow process


Assignment:

A factory makes women’s blouses in a traditional batch flow process. Making one of these blouses requires five distinct sewing operations that must be done in sequence. There are no set ups. The first two of these operations each take two minutes per blouse; the third and fourth each require one minute per blouse; and the fifth operation requires three minutes per blouse. Any of these five operations can be done on any sewing machine in the factory.

a.) In the traditional batch flow process, the factory has 70 workers and has been producing an average of 37.3 batches per 480-minute shift. On average, each worker has 2 batches at his/her station (working on one and with one batch waiting). What is the average throughput time for a batch?

b.) After running this new cell for a while, the company observes that cross-trained workers need roughly 10% more time to do their tasks than workers in the traditional batch-flow environment. What is the output rate of this 5-person cell in an 8-hour day?

Your answer must be typed, double-spaced, Times New Roman font (size 12), one-inch margins on all sides, APA format and also include references.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Problem on batch flow process
Reference No:- TGS01991743

Expected delivery within 24 Hours