Bay Construction, Inc., a contractor, asks Cool Electric, a subcontractor, to provide certain services. Nothing is expressed about payment. Cool provides the services, but Bay refuses to pay. In Cool's suit to recover, the chief issue is most likely to be whether these parties had:
a) an actual contract.
b) an implied-in-fact contract.
c) a voidable contract.
d) a formal contract.