Problem 1: Given the tabulated cut/fill data below, calculate the net cubic yards of excavated materials. Neglect soil type, water content, shrinkage, & swellage.
Station
|
Square feet (S.F.) of materials cut
|
Square feet (S.F.) of material filled
|
1 + 00
|
150
|
0
|
2 + 00
|
50
|
0
|
3 + 00
|
0
|
40
|
Assume average areas between stationing. Show all calculations.